Where a council says a garden gym needs planning permission, an application has to be made, checked, publicised and decided. This article sets out what the government’s Planning Practice Guidance says about that process in England, in four pages read on 11 November 2026. The pages are written for planning applications in general and do not mention garden gyms or permitted development. The guidance names the application fee as a requirement but its amount is not given in these pages.
First, talk to the council
The guidance on pre-application engagement (last updated 15 March 2019) says early discussion can help identify the information that should accompany a formal application, which reduces the likelihood of delays at the validation stage. The guidance on making an application (last updated 12 May 2025) makes the same point: pre-application discussions can be a useful way to agree what information is required before an application is submitted.
The pre-application guidance adds that councils may charge for discretionary services under section 93 of the Local Government Act 2003, and that where charges are made they must not exceed the cost of providing the service.
What makes an application valid
The guidance lists four parts of a valid application for planning permission: a completed application form, compliance with national information requirements, the correct fee, and provision of local information requirements. It says the national requirements are:
- plans and drawings;
- an ownership certificate and agricultural land declaration;
- a Design and Access Statement, for some applications; and
- a fire statement, for some applications made on or after 1 August 2021.
As a minimum, the plans must include a location plan showing the application site in relation to the surrounding area. The guidance says the scale should typically be 1:1250 or 1:2500, the site should be edged clearly in red, and any other land owned by the applicant close to or adjoining the site should be edged in blue. Plans must be drawn to an identified scale and show north.
The guidance also says an application is not valid unless the relevant ownership certificate has been completed, and that knowingly or recklessly completing a false or misleading certificate is an offence carrying a maximum fine of up to £5,000.
The local list: extra information a council may ask for
A council may ask for supporting information, but the guidance says its requirements should be set out on a formally adopted local list published on its website less than 2 years before the application is submitted. It says local requirements have no bearing on validity unless they are on such a list. Information requested for a particular application must also be reasonable given the nature and scale of the development and about a matter that is reasonably thought to be a material consideration.
If a council asks for information the applicant thinks is not necessary, the guidance says the applicant can either provide it or use the dispute procedure. That starts with an article 12 notice setting out why the request does not meet the statutory tests. The council must then issue either a validation notice, saying it no longer requires the information, or a non-validation notice, saying it still does.
After validation: who is told, and for how long
The consultation guidance (last updated 1 April 2022) says the formal consultation period will normally last for 21 days, and that comment periods in the publicity are not less than 21 days, or 14 days where a notice is published in a newspaper. Its table of statutory publicity sets out different methods by type of application:
- for non-major development not covered by another entry, a site notice or neighbour notification letter, plus the council’s website;
- for development affecting the setting of a listed building, or the character or appearance of a conservation area, a site notice, a newspaper advertisement and the website.
The guidance tells people commenting that comments should be made before the statutory deadline for them to be taken into account.
How long should a decision take?
The determination guidance (last updated 8 April 2026) says the statutory time limits are 13 weeks for major development, 10 weeks for technical details consent and, from 1 August 2021, public service infrastructure development, and 8 weeks for all other types of development. Applications subject to an Environmental Impact Assessment have a 16 week limit. A longer period can be agreed, but any extension of time must be in writing and set out when a decision is expected.
Where no extended period has been agreed and a decision takes longer than the statutory period, the government’s stated policy is a decision within 26 weeks for major applications and 16 weeks for non-major ones. The guidance says a valid application not determined within the statutory period, or within a period agreed in writing, gives the applicant a right to appeal to the Secretary of State against non-determination.
The bottom line
The guidance describes a valid application as four things together: the form, the national information, the fee and any local information that is on a current local list. It says consultation normally lasts 21 days, with 14 days where a newspaper notice is used, and that 8 weeks is the statutory decision period for development other than the types given 13, 10 or 16 weeks, unless a longer period is agreed in writing. If a valid application is not decided in time, there is a right of appeal against non-determination. None of the pages mentions garden gyms, so the council’s own pages show what it asks for.
Sources
- Making an application, Planning Practice Guidance, Ministry of Housing, Communities and Local Government, last updated 12 May 2025, read 11 November 2026 (gov.uk)
- Before submitting an application, Planning Practice Guidance, Ministry of Housing, Communities and Local Government, last updated 15 March 2019, read 11 November 2026 (gov.uk)
- Consultation and pre-decision matters, Planning Practice Guidance, Ministry of Housing, Communities and Local Government, last updated 1 April 2022, read 11 November 2026 (gov.uk)
- Determining a planning application, Planning Practice Guidance, Ministry of Housing, Communities and Local Government, last updated 8 April 2026, read 11 November 2026 (gov.uk)